Leadville Airport Taxilane
The project included construction for a new taxilane adjacent and north of the existing General Aviation (GA) Apron; including drainage installation, pavement removal by milling, aggregate base course installation, asphalt concrete paving, pavement markings and update to PG binder. Along with site grading, storm installation, subgrade prep, select base material placement, new asphalt placement, striping and aviation indicators.
Details
Location
Leadville, CO
Size
10 acres
Owner
Lake County Comissioners
engineer
Kimley-Horn